Preface |
|
xiii | |
Chapter 1. An Introduction to the Construction Industry |
|
1 | (10) |
|
Critical Issues Facing Contractors in This New Millennium |
|
|
2 | (9) |
|
How our industry is perceived |
|
|
2 | (1) |
|
|
3 | (1) |
|
Human resources—the changing workforce |
|
|
4 | (1) |
|
The undocumented immigrant problem |
|
|
4 | (1) |
|
|
5 | (1) |
|
|
6 | (1) |
|
|
6 | (1) |
|
|
7 | (1) |
|
|
8 | (1) |
|
|
8 | (1) |
|
|
8 | (3) |
Chapter 2. The Start of the Construction Process |
|
11 | (34) |
|
|
12 | (3) |
|
Defining costs in the letter of intent |
|
|
13 | (1) |
|
Subcontractor commitments via the letter of intent |
|
|
14 | (1) |
|
The letter of intent termination clause |
|
|
14 | (1) |
|
Prevalent Types of Construction Contracts |
|
|
15 | (30) |
|
Cost of the work plus a fee |
|
|
15 | (4) |
|
The stipulated or lump-sum contract |
|
|
19 | (2) |
|
The Cost-plus-a-fee with a GMP contract |
|
|
21 | (6) |
|
Construction manager contracts |
|
|
27 | (4) |
|
The joint venture agreement |
|
|
31 | (1) |
|
|
32 | (1) |
|
|
32 | (1) |
|
Contracts with government agencies |
|
|
33 | (12) |
Chapter 3. The General Conditions to the Construction Contract |
|
45 | (16) |
|
AIA A201—General Conditions of the Contract for Construction |
|
|
45 | (10) |
|
Article 1: General provisions—the contract documents |
|
|
45 | (1) |
|
|
46 | (1) |
|
|
47 | (1) |
|
Article 4: Administration of the contract |
|
|
48 | (1) |
|
Article 5: Subcontractors |
|
|
49 | (1) |
|
Article 6: Construction by owner or by separate contractors |
|
|
50 | (1) |
|
Article 7: Changes in the work |
|
|
51 | (1) |
|
|
51 | (1) |
|
Article 9: Payments and completion |
|
|
52 | (1) |
|
Article 10: Protection of persons and property |
|
|
53 | (1) |
|
Article 11: Insurance and bonds |
|
|
53 | (1) |
|
Article 12: Uncovering and correction of work |
|
|
54 | (1) |
|
Article 13: Tests and inspections |
|
|
54 | (1) |
|
Article 14: Termination or suspension of the contract |
|
|
54 | (1) |
|
The 1987 edition of AIA A201 |
|
|
54 | (1) |
|
AIA Document A210CMa—General Conditions for the Construction Manager Contract |
|
|
55 | (1) |
|
The Associated General Contractor's Version of General Conditions between Owner and Contractor-AGC Document No. 200 |
|
|
56 | (1) |
|
The dispute resolution menu |
|
|
57 | (1) |
|
The Engineers Joint Contract Documents Committee General Conditions |
|
|
58 | (1) |
|
|
59 | (2) |
Chapter 4. Bonds and Insurance |
|
61 | (16) |
|
|
61 | (1) |
|
|
62 | (2) |
|
Bonds and the Bonding Process |
|
|
64 | (13) |
|
|
64 | (1) |
|
|
65 | (1) |
|
|
66 | (1) |
|
|
66 | (1) |
|
|
67 | (1) |
|
|
68 | (1) |
|
Workers' compensation insurance |
|
|
68 | (1) |
|
Subcontractor default insurance |
|
|
69 | (1) |
|
Controlled insurance programs |
|
|
69 | (2) |
|
|
71 | (6) |
Chapter 5. Organizing the Project Team |
|
77 | (32) |
|
Organizing the Job in the Office |
|
|
78 | (4) |
|
Changing CSI specification division numbering |
|
|
78 | (1) |
|
|
78 | (3) |
|
|
81 | (1) |
|
|
82 | (22) |
|
Investigating allowance and bid alternates |
|
|
83 | (2) |
|
|
85 | (1) |
|
Shop drawings and the shop drawing log |
|
|
86 | (4) |
|
|
90 | (1) |
|
|
90 | (3) |
|
|
93 | (3) |
|
The critical path method (CPM) |
|
|
96 | (1) |
|
|
97 | (1) |
|
The importance of float and who owns it |
|
|
98 | (1) |
|
The project meeting minutes |
|
|
98 | (2) |
|
Other forms to consider when getting organized |
|
|
100 | (2) |
|
Lien waivers—for progress and final payment |
|
|
102 | (2) |
|
|
104 | (3) |
|
Shop Drawing Organization |
|
|
107 | (1) |
|
The Future of Project Organization |
|
|
107 | (2) |
Chapter 6. Successful Project Completion Demands a Successful Start |
|
109 | (18) |
|
What Owners Consider Important |
|
|
109 | (1) |
|
Starting Off on the Right Foot |
|
|
110 | (1) |
|
Controlling the Project Start |
|
|
111 | (1) |
|
Review of the Contract with the Owner |
|
|
111 | (1) |
|
Review of the Project Specifications |
|
|
112 | (1) |
|
Specific items to look for when reviewing the specifications |
|
|
113 | (1) |
|
|
113 | (1) |
|
Inspections and Test Reports (Other than Those Required by Local Officials) |
|
|
114 | (1) |
|
Operations and Maintenance Manuals |
|
|
114 | (1) |
|
|
115 | (1) |
|
TAB—A Procedure that Requires Special Attention |
|
|
115 | (2) |
|
|
117 | (2) |
|
Is it' a punch list or a warranty item? |
|
|
117 | (1) |
|
Attic stock, special tools, and spare parts |
|
|
118 | (1) |
|
Material safety data sheets |
|
|
118 | (1) |
|
Preparing for that First Project Meeting with the Subcontractors |
|
|
119 | (6) |
|
That Dangerous End-of-Project Syndrome |
|
|
125 | (2) |
Chapter 7. Estimating |
|
127 | (22) |
|
The 2004 Edition of CSI's MasterFormat |
|
|
127 | (1) |
|
|
128 | (4) |
|
|
128 | (1) |
|
Acquiring the in-house database |
|
|
128 | (1) |
|
The weekly field labor report |
|
|
129 | (2) |
|
Combining cost codes and daily reports to produce the database |
|
|
131 | (1) |
|
|
132 | (2) |
|
|
132 | (1) |
|
Monitoring the reporting of costs |
|
|
133 | (1) |
|
When disparities in costs appear |
|
|
133 | (1) |
|
Bundling to create a unit cost |
|
|
134 | (1) |
|
|
134 | (3) |
|
The various stages of the process |
|
|
136 | (1) |
|
The Postconstruction Project Review |
|
|
137 | (1) |
|
Mining Completed Projects to Enhance the Database |
|
|
137 | (2) |
|
The Project Parameter Cost Model Form |
|
|
139 | (2) |
|
The preparation of a project cost model data sheet |
|
|
140 | (1) |
|
Sources of Conceptual Estimating Data |
|
|
141 | (1) |
|
|
142 | (1) |
|
Order-of-Magnitude Estimating |
|
|
142 | (1) |
|
Order-of-magnitude issues to consider |
|
|
143 | (1) |
|
Special Requirements Associated with Office Building Estimating |
|
|
143 | (1) |
|
|
143 | (1) |
|
|
144 | (1) |
|
The Developer's Responsibility |
|
|
144 | (3) |
|
Subcontractor Responsibilities as They Relate to Tenant Fit-Ups |
|
|
147 | (2) |
Chapter 8. Buying Out the Job |
|
149 | (34) |
|
|
149 | (9) |
|
The subcontract interview form |
|
|
150 | (8) |
|
|
158 | (1) |
|
|
159 | (4) |
|
Other items to consider during the solicitation of prices |
|
|
159 | (4) |
|
Combining Work to Best Advantage |
|
|
163 | (1) |
|
Subcontract or Do It Ourselves? |
|
|
163 | (2) |
|
The "we can do it cheaper" syndrome |
|
|
164 | (1) |
|
Key Questions to Ask Subcontractors during Negotiations |
|
|
165 | (1) |
|
Pitfalls to Avoid in Mechanical and Electrical Contract Negotiations |
|
|
166 | (1) |
|
|
167 | (1) |
|
|
167 | (2) |
|
Temporary light and temporary power |
|
|
167 | (1) |
|
Installation of underground utilities |
|
|
168 | (1) |
|
Designing to local utility standards |
|
|
168 | (1) |
|
Warranties and Guarantees |
|
|
169 | (1) |
|
Job Cleaning and the Contract |
|
|
169 | (2) |
|
Communicating the Terms and Conditions of the Subcontract Agreement |
|
|
171 | (2) |
|
Importance of lien waiver requirements in the subcontract agreement |
|
|
171 | (2) |
|
|
173 | (4) |
|
Ordering when exact quantities are not known |
|
|
174 | (1) |
|
Price protection and the purchase order |
|
|
175 | (2) |
|
Pitfalls to Avoid When Issuing Subcontracts and Purchase Orders |
|
|
177 | (1) |
|
Do Your Subcontract Agreements Include These Key Provisions? |
|
|
178 | (5) |
Chapter 9. The Change Orders |
|
183 | (28) |
|
|
184 | (1) |
|
Starting off on the right foot |
|
|
184 | (1) |
|
Reviewing the Important Contents of a Change-Order Request |
|
|
185 | (2) |
|
|
186 | (1) |
|
The verbal authorization to proceed |
|
|
186 | (1) |
|
|
187 | (1) |
|
Completion Time and the Change Order |
|
|
188 | (6) |
|
|
188 | (1) |
|
Will contract time remain the same, be reduced, or be extended? |
|
|
189 | (1) |
|
|
190 | (1) |
|
What costs other than bricks and mortar should be considered? |
|
|
191 | (1) |
|
What overhead and profit fees can be included in change-order work? |
|
|
192 | (1) |
|
When credits and charges both apply |
|
|
193 | (1) |
|
The construction change directive—The CCD |
|
|
193 | (1) |
|
Be alert to other contract provisions relating to change-order work |
|
|
194 | (1) |
|
Public Works and the Change-Order Process |
|
|
194 | (1) |
|
Roadblocks to Acceptance of Change Orders |
|
|
195 | (5) |
|
|
196 | (1) |
|
The contractor's perspective |
|
|
196 | (1) |
|
The architect and engineer's perspective |
|
|
197 | (3) |
|
Liquidated Damages and the Change-Order Process |
|
|
200 | (3) |
|
A typical liquidated damages clause |
|
|
201 | (2) |
|
Change Orders Reflecting Costs Due to Job Delays |
|
|
203 | (3) |
|
|
204 | (1) |
|
|
204 | (1) |
|
|
204 | (2) |
|
Pitfalls to Avoid when Preparing Change Orders |
|
|
206 | (1) |
|
The Change-Order Cost Checklist |
|
|
207 | (1) |
|
Effective Change-Order Control |
|
|
208 | (3) |
Chapter 10. Quality Control and Quality Assurance |
|
211 | (18) |
|
Quality Begins with Quality Design |
|
|
211 | (1) |
|
|
212 | (1) |
|
|
213 | (1) |
|
The International Standards Organization |
|
|
213 | (1) |
|
The Six Sigma Approach to Quality |
|
|
214 | (1) |
|
|
215 | (1) |
|
Quality starts with a thorough review of the contract documents |
|
|
216 | (1) |
|
Quality Control and the Specifications |
|
|
216 | (1) |
|
Using trade organizations to learn about quality standards |
|
|
217 | (1) |
|
The Preconstruction Conference—QC and QA |
|
|
217 | (3) |
|
Sample panels and mock-ups |
|
|
218 | (1) |
|
|
219 | (1) |
|
Developing a Company QC/QA Program |
|
|
220 | (9) |
|
The inspection checklist method |
|
|
220 | (9) |
Chapter 11. Project Documentation |
|
229 | (32) |
|
The Documentation Process |
|
|
229 | (2) |
|
Documentation to the Owner |
|
|
231 | (2) |
|
The unique provisions of a GMP contract with respect to documentation |
|
|
231 | (1) |
|
Documentation to an owner from the construction manager |
|
|
231 | (2) |
|
Documentation to the Architect and Engineer |
|
|
233 | (1) |
|
Shop drawing submittals, review, returns and logs |
|
|
233 | (1) |
|
Requests for Clarification and Requests for Information |
|
|
234 | (3) |
|
Field Conditions Documentation |
|
|
237 | (1) |
|
The affect on "as-builts" |
|
|
237 | (1) |
|
|
238 | (1) |
|
Other Important Documents |
|
|
239 | (3) |
|
Cost proposal or cost estimate requests |
|
|
239 | (1) |
|
Conditions that impact completion time |
|
|
239 | (2) |
|
Documentation of close-out requirements |
|
|
241 | (1) |
|
Documentation to the Subcontractors |
|
|
242 | (8) |
|
Is the scope of the work fully understood by all? |
|
|
243 | (1) |
|
Avoiding problems related to subcontractor misunderstandings |
|
|
244 | (1) |
|
Linking the subcontract agreement with the owner's contract |
|
|
245 | (1) |
|
Subcontractor performance—the major concern |
|
|
245 | (2) |
|
Danger signs and how to interpret them |
|
|
247 | (2) |
|
That low subcontract bid—are problems waiting to surface? |
|
|
249 | (1) |
|
Documentation When Major Drawing Revisions Are Made |
|
|
250 | (2) |
|
What to do with all of those 81/2 x 11s |
|
|
251 | (1) |
|
Documentation Required When Contracting with Public Agencies |
|
|
252 | (3) |
|
|
252 | (2) |
|
Complying with other government requirements |
|
|
254 | (1) |
|
Project Documentation from the Field |
|
|
255 | (6) |
|
The superintendent's record of daily activities |
|
|
255 | (4) |
|
Photographs: important documentary components |
|
|
259 | (2) |
Chapter 12. Claims, Disputes, Arbitration, and Mediation |
|
261 | (34) |
|
What Triggers Claims and Disputes? |
|
|
261 | (1) |
|
The Bid Proposal Process and the Potential for Disputes |
|
|
262 | (5) |
|
|
263 | (4) |
|
Other Potentials for Disputes |
|
|
267 | (23) |
|
|
267 | (1) |
|
Disputes regarding contract interpretation |
|
|
268 | (3) |
|
Subsurface, changed, and differing conditions |
|
|
271 | (1) |
|
Using geotechnical disclaimers to advantage |
|
|
272 | (1) |
|
The court and differing site conditions |
|
|
272 | (7) |
|
Differing or changed conditions |
|
|
279 | (2) |
|
Be wary of subcontractor input |
|
|
281 | (1) |
|
A word about lost productivity |
|
|
282 | (3) |
|
The courts and lost productivity issues |
|
|
285 | (1) |
|
Claims against professionals |
|
|
286 | (1) |
|
Acceleration: what it is and how it is used |
|
|
287 | (3) |
|
Arbitration and Mediation |
|
|
290 | (3) |
|
|
291 | (1) |
|
|
291 | (2) |
|
|
293 | (2) |
Chapter 13. Safety in Construction |
|
295 | (30) |
|
The Occupational Safety and Health Act (OSHA) |
|
|
295 | (2) |
|
Factors Responsible for Declining Accident Rates |
|
|
297 | (9) |
|
Safety Pays—In More Ways Than One |
|
|
306 | (2) |
|
The positive effects of a good safety record |
|
|
306 | (1) |
|
Workers' compensation insurance |
|
|
307 | (1) |
|
Developing the Company Safety Program |
|
|
308 | (17) |
|
The statement of company policy |
|
|
309 | (1) |
|
The safety director/safety coordinator |
|
|
310 | (2) |
|
A hazard communication program |
|
|
312 | (13) |
Chapter 14. Design-Build |
|
325 | (30) |
|
|
325 | (6) |
|
Why has design-build garnered so much attention recently? |
|
|
326 | (5) |
|
Developing a Design-Build Capability |
|
|
331 | (7) |
|
Creating in-house design capability |
|
|
331 | (1) |
|
|
331 | (1) |
|
The limited liability corporation—the LLC |
|
|
332 | (1) |
|
An architect- or contractor-led design-build team? |
|
|
332 | (6) |
|
Developing a Design-Build Program |
|
|
338 | (2) |
|
Developing design-build proposals |
|
|
338 | (1) |
|
|
339 | (1) |
|
How Owners Select Design-Builders |
|
|
340 | (9) |
|
|
340 | (4) |
|
|
344 | (5) |
|
Contract Provisions Unique to the Design-Build Process |
|
|
349 | (4) |
|
Special provisions of design-build contracts |
|
|
349 | (1) |
|
Contract provisions relating to defining the owner's program |
|
|
350 | (1) |
|
The role of the subcontractor in the design-build process |
|
|
351 | (2) |
|
Design-Build in the Public Sector |
|
|
353 | (2) |
Chapter 15. Sustainability and Green Buildings |
|
355 | (20) |
|
The Impact of Construction on the Environment |
|
|
356 | (1) |
|
What Do We Mean by Sustainability? |
|
|
356 | (5) |
|
|
357 | (3) |
|
Green buildings in the private sector |
|
|
360 | (1) |
|
Some Design-Build/Sustainable Building Guidelines |
|
|
361 | (10) |
|
Are green buildings more expensive than conventional construction? |
|
|
361 | (3) |
|
|
364 | (2) |
|
Other revealing but not so apparent benefits of green buildings |
|
|
366 | (5) |
|
The Greening of Existing Buildings |
|
|
371 | (4) |
Chapter 16. Interoperability and Building Information Modeling (BIM) |
|
375 | (18) |
|
Looking at the Last Several Decades |
|
|
375 | (1) |
|
Contractors Slow to Embrace Technology |
|
|
376 | (10) |
|
Interoperabilty—what is it and why is it so important? |
|
|
378 | (5) |
|
The steel industry becomes a leader |
|
|
383 | (3) |
|
What Is Building Information Modeling All About? |
|
|
386 | (7) |
|
Coordination and interference issues addressed |
|
|
386 | (7) |
Index |
|
393 | |